General Contracting & Project Management
Do I need a general contractor if I already have an architect?
In Costa Rica the architect's CFIA-stamped role covers design and, if contracted, inspección. It does not cover buying materials, managing trade sequencing or holding the schedule. Those are contracting functions and they are where most budget overruns originate.
How do you handle currency risk on a long build?
Contracts are written in one primary currency with material escalation clauses tied to published indices. Steel and cement are the two line items most exposed to movement, so we typically pre-purchase both at award.
What does CCSS compliance mean for me as the owner?
Under Costa Rican law an owner can carry liability for unregistered workers on their site. We verify every subcontractor's CCSS planilla and INS policy before mobilization and keep the records in your project file.